Lemon Creek Marina Waterfront Reconstruction
-
80% complete
-
0% complete
-
0% complete
This project will reconstruct the waterfront Parks infrastructure damaged by Hurricane Sandy at Lemon Creek Marina.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2020
Projected Completion Date:
January 2022
Adjusted Completion Date:
May 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Lemon Creek Park, Staten Island
Hylan Boulevard & Seguine Avenue
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey