Chelsea Park Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball court and adjacent paths and landscape at Chelsea Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2019
Projected Completion Date: April 2020
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021
Completion Date: June 2022

Construction

Start Date: June 2022
Projected Completion Date: June 2023
Completion Date: June 2023

Understand how we build parks.

Funding

Total Funding: $970,000
Funding Source: City Council

Location

Chelsea Park, Manhattan
Mid block on West 28th Street between 9th Avenue and 10th Avenue
Community Board: 04

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024