Grover Cleveland Playground and Pals Oval Synthetic Turf Fields Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the synthetic turf fields at Grover Cleveland Playground and Pals Oval.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
January 2019
Completion Date:
January 2019
Procurement
Start Date: January 2019
Projected Completion Date:
October 2019
Completion
Date:
April 2020
Construction
Start Date: September 2020
Projected Completion Date:
June 2021
Completion Date: November 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Grover Cleveland Playground, Queens
Rene Court, Grandview Avenue, Stanhope Street & Fairview Avenue
Community Board: 05 -
Tudor Park, Queens
North Conduit Avenue, between 80 and 88 Streets, 133 Avenue
Community Board: 10
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024