Inwood Hill Park Soccer Field 1 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    16% complete

This project will reconstruct soccer field 1 at Inwood Hill Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2019
Projected Completion Date: May 2021
Completion Date: June 2022

Procurement

Start Date: June 2022
Projected Completion Date: March 2023
Completion Date: June 2024

Construction

Start Date: July 2024
Projected Completion Date: July 2025

Understand how we build parks.

Funding

Total Funding: $8,722,000
Funding Sources:
  • City Council
  • Mayoral

Location

Inwood Hill Park, Manhattan
Between the Hudson River and Amtrak Line, north of Dyckman Street
Community Board: 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024