Highbridge Park Dyckman Rest Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

The project will reconstruct Dyckman Rest in Highbridge Park with a playground and seating areas.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2021
Projected Completion Date: February 2022
Completion Date: February 2022

Procurement

Start Date: February 2022
Projected Completion Date: November 2022
Completion Date: July 2023

Construction

Start Date: September 2023
Projected Completion Date: December 2024
Completion Date: July 2024

Understand how we build parks.

Funding

Total Funding: $5,000,000
Funding Source: Mayoral

Location

Highbridge Park, Manhattan
Dyckman Street, Nagle Avenue, Fort George Hill
Community Board: 10, 12

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024