Project Timeline
Design
Assigned & Start Date: February 2021
Projected Completion Date:
February 2022
Completion Date:
February 2022
Procurement
Start Date: February 2022
Projected Completion Date:
November 2022
Completion
Date:
July 2023
Construction
Start Date: September 2023
Projected Completion Date:
December 2024
Completion Date: July 2024