Monsignor Kett Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Monsignor Kett Playground, including the court areas, play areas, and security and sports lighting.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2019
Projected Completion Date:
January 2020
Completion Date:
April 2020
Procurement
Start Date: April 2020
Projected Completion Date:
January 2021
Completion
Date:
March 2022
Construction
Start Date: April 2022
Projected Completion Date:
July 2023
Completion Date: July 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Monsignor Kett Playground, Manhattan
West 204th Street between 10th Avenue and Nagle Avenue
Community Board: 12
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024