Astoria Pool Filtration System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the filtration system at Astoria Pool.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2019
Projected Completion Date: March 2021
Completion Date: June 2021

Procurement

Start Date: June 2021
Projected Completion Date: March 2022
Completion Date: September 2022

Construction

Start Date: October 2022
Projected Completion Date: June 2024
Completion Date: June 2024

Understand how we build parks.

Funding

Total Funding: $18,947,000
Funding Source: Mayoral

Location

Astoria Park, Queens
19th Street at 23rd Drive
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024