Astoria Pool Filtration System Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the filtration system at Astoria Pool.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2019
Projected Completion Date:
March 2021
Completion Date:
June 2021
Procurement
Start Date: June 2021
Projected Completion Date:
March 2022
Completion
Date:
September 2022
Construction
Start Date: October 2022
Projected Completion Date:
June 2024
Completion Date: June 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Astoria Park, Queens
19th Street at 23rd Drive
Community Board: 01
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024