Flushing Meadows Corona Park Electrical Vault Reconstruction (Hurricane Sandy)
-
80% complete
-
0% complete
-
0% complete
This project will reconstruct the electrical vaults in Flushing Meadows Corona Park that were damaged by Hurricane Sandy.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2019
Projected Completion Date:
October 2021
Adjusted Completion Date:
June 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Flushing Meadows Corona Park, Queens
Grand Central Parkway, Whitestone Expressway between 111th Street and College Point Boulevard, Park Drive East
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024