Bronx Street Tree Planting FY20 - Community Boards 9-12
-
100% complete
-
100% complete
-
100% complete
This project will plant new street trees in Community Boards 9-12 in the Bronx.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2018
Projected Completion Date:
December 2018
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
September 2019
Completion
Date:
April 2020
Construction
Start Date: August 2020
Projected Completion Date:
August 2021
Completion Date: August 2021
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Private
Last updated: 01/17/2025