Bronx Street Tree Planting FY20 - Community Boards 9-12

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new street trees in Community Boards 9-12 in the Bronx.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2018
Projected Completion Date: December 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: April 2020

Construction

Start Date: August 2020
Projected Completion Date: August 2021
Completion Date: August 2021

Understand how we build parks.

Funding

Total Funding: $2,850,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations in the Bronx

Project Staff

Contact NYC Parks about this project