Brooklyn Street Tree Planting FY20 - Community Boards 5,8,16
-
100% complete
-
100% complete
-
100% complete
This project will plant new street trees in Community Boards 5, 8, and 16 in Brooklyn.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2018
Projected Completion Date:
December 2018
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
September 2019
Completion
Date:
December 2019
Construction
Start Date: October 2019
Projected Completion Date:
October 2020
Completion Date: October 2020
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Private
Last updated: 11/22/2024