Brooklyn Street Tree Planting FY20 - Community Boards 6,7,10,12

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new street trees in Community Boards 6, 7, 10, and 12 in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2018
Projected Completion Date: December 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: February 2021

Construction

Start Date: March 2021
Projected Completion Date: March 2022
Completion Date: January 2022

Understand how we build parks.

Funding

Total Funding: $2,975,000
Funding Sources:
  • City Council
  • Mayoral
  • Private

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024