Queens Street Tree Planting FY20 - Community Boards 7,8,11
-
100% complete
-
100% complete
-
100% complete
This project will plant new street trees in Community Boards 7, 8, and 11 in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2018
Projected Completion Date:
December 2018
Completion Date:
December 2020
Procurement
Start Date: December 2020
Projected Completion Date:
August 2021
Completion
Date:
March 2022
Construction
Start Date: April 2022
Projected Completion Date:
April 2023
Completion Date: February 2023
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Private