Queens Street Tree Planting FY20 - Community Boards 7,8,11

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new street trees in Community Boards 7, 8, and 11 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2018
Projected Completion Date: December 2018
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: August 2021
Completion Date: March 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: February 2023

Understand how we build parks.

Funding

Total Funding: $2,800,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations in Queens

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024