Design

Assigned & Start Date: September 2018
Projected Completion Date: December 2018
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: August 2021
Completion Date: March 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: February 2023

Understand how we build parks.

Funding

Total Funding: $2,800,000