Success Garden Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the multi-purpose play and passive recreation areas in Success Garden.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2018
Projected Completion Date:
September 2019
Completion Date:
October 2019
Procurement
Start Date: October 2019
Projected Completion Date:
June 2020
Completion
Date:
April 2021
Construction
Start Date: June 2021
Projected Completion Date:
May 2022
Completion Date: February 2022