Success Garden Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the multi-purpose play and passive recreation areas in Success Garden.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2018
Projected Completion Date: September 2019
Completion Date: October 2019

Procurement

Start Date: October 2019
Projected Completion Date: June 2020
Completion Date: April 2021

Construction

Start Date: June 2021
Projected Completion Date: May 2022
Completion Date: February 2022

Understand how we build parks.

Funding

Total Funding: $1,758,000
Funding Sources:
  • Borough President
  • City Council

Location

Success Garden, Brooklyn
Alabama Avenue & Livonia Avenue
Community Board: 05

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024