Ocean Parkway Malls Bike Path Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the bike path on the west side of the Ocean Parkway Malls from Avenue R to Avenue X.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2019
Projected Completion Date: April 2020
Completion Date: May 2020

Procurement

Start Date: May 2020
Projected Completion Date: January 2021
Completion Date: September 2022

Construction

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: November 2024

Understand how we build parks.

Funding

Total Funding: $4,075,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Ocean Parkway Malls, Brooklyn
Ocean Parkway between Avenue R and Avenue X
Community Board: 07, 12, 13, 14, 15

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024