Rainbow Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play and seating areas in Rainbow Playground, including the play equipment, safety surfacing, spray shower, fencing, benches, pavement, and drinking fountain.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2019
Projected Completion Date: November 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: September 2021
Completion Date: August 2022

Construction

Start Date: October 2022
Projected Completion Date: October 2023
Completion Date: October 2023

Understand how we build parks.

Funding

Total Funding: $1,319,000
Funding Source: City Council

Location

Rainbow Playground, Brooklyn
6th Avenue and 56th Street
Community Board: 07

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024