Rainbow Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play and seating areas in Rainbow Playground, including the play equipment, safety surfacing, spray shower, fencing, benches, pavement, and drinking fountain.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2019
Projected Completion Date:
November 2020
Completion Date:
December 2020
Procurement
Start Date: December 2020
Projected Completion Date:
September 2021
Completion
Date:
August 2022
Construction
Start Date: October 2022
Projected Completion Date:
October 2023
Completion Date: October 2023
Understand how we build parks.
Funding
Funding Source: City Council
Location
Rainbow Playground, Brooklyn
6th Avenue and 56th Street
Community Board: 07
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024