Fort Hamilton Park Sport Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct basketball and tennis courts in Fort Hamilton Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
October 2019
Completion Date:
October 2019
Procurement
Start Date: October 2019
Projected Completion Date:
July 2020
Completion
Date:
April 2021
Construction
Start Date: June 2021
Projected Completion Date:
June 2022
Completion Date: June 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Fort Hamilton Athletic Field, Brooklyn
83rd Street between Narrows Avenue and Colonial Road
Community Board: 10
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025