Kelly Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the children's play area in Kelly Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2019
Projected Completion Date:
January 2020
Completion Date:
January 2020
Procurement
Start Date: January 2020
Projected Completion Date:
October 2020
Completion
Date:
March 2022
Construction
Start Date: May 2022
Projected Completion Date:
May 2023
Completion Date: September 2023
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Kelly Park Playground, Brooklyn
Moore Place and East 16th Street
Community Board: 15
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024