Sunners Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Sunners Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2018
Projected Completion Date:
December 2019
Completion Date:
August 2020
Procurement
Start Date: August 2020
Projected Completion Date:
May 2021
Completion
Date:
April 2022
Construction
Start Date: May 2022
Projected Completion Date:
May 2023
Completion Date: May 2023
Understand how we build parks.
Funding
Funding Source: City Council
Location
Sunners Playground, Brooklyn
Kings Highway, Avenue H, East 49th Street
Community Board: 18
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024