Grace Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground area in Grace Playground, including the play equipment, safety surfacing, spray shower, fencing, and utilities.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: May 2020

Procurement

Start Date: May 2020
Projected Completion Date: February 2021
Completion Date: January 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: March 2023

Understand how we build parks.

Funding

Total Funding: $1,798,000
Funding Source: City Council

Location

Grace Playground, Brooklyn
Vermont Street between Pitkin Avenue and Belmont Avenue
Community Board: 05

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024