Grace Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground area in Grace Playground, including the play equipment, safety surfacing, spray shower, fencing, and utilities.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2019
Projected Completion Date:
May 2020
Completion Date:
May 2020
Procurement
Start Date: May 2020
Projected Completion Date:
February 2021
Completion
Date:
January 2022
Construction
Start Date: April 2022
Projected Completion Date:
April 2023
Completion Date: March 2023
Understand how we build parks.
Funding
Funding Source: City Council
Location
Grace Playground, Brooklyn
Vermont Street between Pitkin Avenue and Belmont Avenue
Community Board: 05
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024