Saratoga Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground in Saratoga Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2019
Projected Completion Date: February 2020
Completion Date: March 2020

Procurement

Start Date: March 2020
Projected Completion Date: December 2020
Completion Date: January 2022

Construction

Start Date: February 2022
Projected Completion Date: February 2023
Completion Date: January 2023

Understand how we build parks.

Funding

Total Funding: $1,873,000
Funding Source: City Council

Location

Saratoga Park, Brooklyn
Halsey Street, Howard Avenue, Macon Street
Community Board: 03

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025