Faber Park Basketball Courts Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    69% complete

This project will demolish an existing play area and construct two basketball courts at Faber Park with new lighting, bleachers, a drinking fountain, benches, and plantings.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2019
Projected Completion Date: October 2020
Completion Date: May 2021

Procurement

Start Date: May 2021
Projected Completion Date: January 2022
Completion Date: February 2024

Construction

Start Date: March 2024
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $1,967,000
Funding Source: City Council

Location

Faber Pool and Park, Staten Island
Richmond Terrace between Sharpe Avenue and Faber Street
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024