Faber Park Basketball Courts Construction
-
100% complete
-
100% complete
-
69% complete
This project will demolish an existing play area and construct two basketball courts at Faber Park with new lighting, bleachers, a drinking fountain, benches, and plantings.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2019
Projected Completion Date:
October 2020
Completion Date:
May 2021
Procurement
Start Date: May 2021
Projected Completion Date:
January 2022
Completion
Date:
February 2024
Construction
Start Date: March 2024
Projected Completion Date:
March 2025
Understand how we build parks.
Funding
Funding Source: City Council
Location
Faber Pool and Park, Staten Island
Richmond Terrace between Sharpe Avenue and Faber Street
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024