Faber Park Basketball Courts Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    77% complete

This project will demolish an existing play area and construct two basketball courts at Faber Park with new lighting, bleachers, a drinking fountain, benches, and plantings.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2019
Projected Completion Date: October 2020
Completion Date: May 2021

Procurement

Start Date: May 2021
Projected Completion Date: January 2022
Completion Date: February 2024

Construction

Start Date: March 2024
Projected Completion Date: March 2025

Understand how we build parks.

Funding

Total Funding: $1,967,000
Funding Source: City Council

Location

Faber Pool and Park, Staten Island
Richmond Terrace between Sharpe Avenue and Faber Street
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/17/2025