Goble Playground Reconstruction
-
100% complete
-
100% complete
-
61% complete
This project will reconstruct Goble Playground, including the play equipment, swings, basketball and handball courts, drainage and water systems, landscaping and park security lighting.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2021
Projected Completion Date:
March 2022
Completion Date:
August 2022
Procurement
Start Date: August 2022
Projected Completion Date:
May 2023
Completion
Date:
March 2024
Construction
Start Date: June 2024
Projected Completion Date:
June 2025
Understand how we build parks.
Funding
Funding Source: City Council
Location
Goble Playground, Bronx
Goble Place between Inwood Avenue and Macombs Road
Community Board: 04
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024