Jerome Playground South Skate Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will demolish the handball courts and construct a new skate park in their place at Jerome Playground South.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2019
Projected Completion Date: November 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: September 2021
Completion Date: July 2022

Construction

Start Date: September 2022
Projected Completion Date: September 2023
Completion Date: September 2023

Understand how we build parks.

Funding

Total Funding: $2,399,000
Funding Sources:
  • Borough President
  • City Council

Location

Jerome Playground South, Bronx
Cross-Bronx Expressway between Townsend Avenue and Jerome Avenue
Community Board: 04

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025