Galileo Playground Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will reconstruct Galileo Playground.
Project Notes
Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.
Project Timeline
Design
Assigned & Start Date: October 2023
Projected Completion Date:
April 2024
Completion Date:
April 2024
Procurement
Start Date: April 2024
Projected Completion Date:
May 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Galileo Playground, Bronx
Macombs Road between West 175th Street, West 176th Street