Queensbridge Baby Park Handball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the handball courts and fencing and construct a basketball court and planted areas at Queensbridge Baby Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: May 2020

Procurement

Start Date: May 2020
Projected Completion Date: February 2021
Completion Date: March 2022

Construction

Start Date: June 2022
Projected Completion Date: June 2023
Completion Date: February 2023

Understand how we build parks.

Funding

Total Funding: $843,000
Funding Source: City Council

Location

Queensbridge Park, Queens
41st Road and 12th Street
Community Board: 01, 02

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025