Park of the Americas Adult Fitness Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the adult fitness area at Park of the Americas.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2018
Projected Completion Date: December 2019
Completion Date: December 2019

Procurement

Start Date: December 2019
Projected Completion Date: August 2020
Completion Date: January 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: December 2022

Understand how we build parks.

Funding

Total Funding: $710,000
Funding Source: City Council

Location

Park Of The Americas, Queens
103rd Street, 104th Street, 41st Avenue, 42nd Avenue
Community Board: 04

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024