Brookville Park Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the synthetic turf field at Brookville Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2018
Projected Completion Date: November 2019
Completion Date: December 2019

Procurement

Start Date: December 2019
Projected Completion Date: September 2020
Completion Date: December 2021

Construction

Start Date: January 2022
Projected Completion Date: January 2023
Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $2,035,000
Funding Source: City Council

Location

Brookville Park, Queens
232nd Street between 144th Avenue and 145th Avenue
Community Board: 13

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024