Springfield Park Basketball Courts and BBQ Area Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the basketball courts, and install new picnic tables, grills, charcoal bins, trees, and an accessible path to the BBQ area in Springfield Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2018
Projected Completion Date:
February 2020
Completion Date:
March 2020
Procurement
Start Date: March 2020
Projected Completion Date:
December 2020
Completion
Date:
April 2022
Construction
Start Date: July 2022
Projected Completion Date:
July 2023
Completion Date: July 2023
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Springfield Park, Queens
Springfield Boulevard between 145th Road and 147th Avenue
Community Board: 13
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project