Springfield Park Basketball Courts and BBQ Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball courts, and install new picnic tables, grills, charcoal bins, trees, and an accessible path to the BBQ area in Springfield Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2018
Projected Completion Date: February 2020
Completion Date: March 2020

Procurement

Start Date: March 2020
Projected Completion Date: December 2020
Completion Date: April 2022

Construction

Start Date: July 2022
Projected Completion Date: July 2023
Completion Date: July 2023

Understand how we build parks.

Funding

Total Funding: $3,301,000
Funding Sources:
  • City Council
  • Mayoral

Location

Springfield Park, Queens
Springfield Boulevard between 145th Road and 147th Avenue
Community Board: 13

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project