Roy Wilkins Park Black Spectrum Theatre Pathways and Lawn Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the pathways and lawn area adjacent to the Black Spectrum Theatre.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2019
Projected Completion Date:
May 2020
Completion Date:
June 2020
Procurement
Start Date: June 2020
Projected Completion Date:
March 2021
Completion
Date:
April 2022
Construction
Start Date: September 2022
Projected Completion Date:
June 2023
Completion Date: December 2022
Understand how we build parks.
Funding
Funding Source: City Council
Location
Roy Wilkins Recreation Center, Queens
Baisley Boulevard at 177th Street
Community Board: 12
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025