Noonan Playground Dog Run Construction and Seating Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a dog run and reconstruct the seating area at Noonan Playground, including new plantings, benches, pavement, stairs, fencing, lighting, and drinking fountains.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: July 2020

Procurement

Start Date: July 2020
Projected Completion Date: March 2021
Completion Date: June 2022

Construction

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: March 2024

Understand how we build parks.

Funding

Total Funding: $2,500,000
Funding Source: Mayoral

Location

L/CPL Thomas P. Noonan Jr. Playground, Queens
Greenpoint Avenue and 42nd Street
Community Board: 02

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024