Clove Lakes Park WWII Veterans War Memorial Ice Rink Condensers Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the rink condensers at the WWII Veterans War Memorial Ice Rink in Clove Lakes Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2018
Projected Completion Date: December 2018
Completion Date: January 2019

Procurement

Start Date: January 2019
Projected Completion Date: October 2019
Completion Date: January 2020

Construction

Start Date: January 2020
Projected Completion Date: January 2021
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $494,000
Funding Source: Mayoral

Location

Clove Lakes Park, Staten Island
Victory Boulevard at Clove Road
Community Board: 01

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/17/2025