Frederick Johnson Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Frederick Johnson Playground, including play equipment and safety surfacing, a bikeway, synthetic turf practice field, benches, lighting, pavements, fencing, and plantings.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: February 2019
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: November 2019
Completion Date: January 2020

Construction

Start Date: February 2020
Projected Completion Date: July 2021
Completion Date: July 2021

Understand how we build parks.

Funding

Total Funding: $5,185,000
Funding Source: Mayoral

Location

Frederick Johnson Playground, Manhattan
Adam Clayton Powell Jr. Boulevard (7th Avenue) and Harlem River Drive between West 150th Street and West 151st Street
Community Board: 10

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024