Frederick Johnson Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Frederick Johnson Playground, including play equipment and safety surfacing, a bikeway, synthetic turf practice field, benches, lighting, pavements, fencing, and plantings.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
February 2019
Completion Date:
March 2019
Procurement
Start Date: March 2019
Projected Completion Date:
November 2019
Completion
Date:
January 2020
Construction
Start Date: February 2020
Projected Completion Date:
July 2021
Completion Date: July 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Frederick Johnson Playground, Manhattan
Adam Clayton Powell Jr. Boulevard (7th Avenue) and Harlem River Drive between West 150th Street and West 151st Street
Community Board: 10
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project