Percy E. Sutton Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    94% complete

This project will reconstruct Percy E. Sutton Playground, including demolishing the existing public restroom building and constructing a seating area, half-court basketball courts, a fitness area, lawn areas, and a bikeway.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: February 2019
Completion Date: April 2019

Procurement

Start Date: April 2019
Projected Completion Date: January 2020
Completion Date: March 2021

Construction

Start Date: April 2021
Projected Completion Date: October 2022
Adjusted Completion Date: October 2024

Understand how we build parks.

Funding

Total Funding: $10,860,000
Funding Sources:
  • Mayoral
  • State

Location

Percy E. Sutton Playground, Manhattan
Harlem River Drive between West 151st Street and West 155th Street
Community Board: 10

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025