Percy E. Sutton Playground Reconstruction
-
100% complete
-
100% complete
-
94% complete
This project will reconstruct Percy E. Sutton Playground, including demolishing the existing public restroom building and constructing a seating area, half-court basketball courts, a fitness area, lawn areas, and a bikeway.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
February 2019
Completion Date:
April 2019
Procurement
Start Date: April 2019
Projected Completion Date:
January 2020
Completion
Date:
March 2021
Construction
Start Date: April 2021
Projected Completion Date:
October 2022
Adjusted Completion Date: October 2024
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- State
Location
Percy E. Sutton Playground, Manhattan
Harlem River Drive between West 151st Street and West 155th Street
Community Board: 10
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024