Percy E. Sutton Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    94% complete

This project will reconstruct Percy E. Sutton Playground, including demolishing the existing public restroom building and constructing a seating area, half-court basketball courts, a fitness area, lawn areas, and a bikeway.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: February 2019
Completion Date: April 2019

Procurement

Start Date: April 2019
Projected Completion Date: January 2020
Completion Date: March 2021

Construction

Start Date: April 2021
Projected Completion Date: October 2022
Adjusted Completion Date: October 2024

Understand how we build parks.

Funding

Total Funding: $10,860,000
Funding Sources:
  • Mayoral
  • State

Location

Percy E. Sutton Playground, Manhattan
Harlem River Drive between West 151st Street and West 155th Street
Community Board: 10

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024