Tompkins Square Park Field House Reconstruction
-
100% complete
-
100% complete
-
97% complete
This project will reconstruct the field house in Tompkins Square Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2019
Projected Completion Date:
March 2020
Completion Date:
October 2020
Procurement
Start Date: October 2020
Projected Completion Date:
June 2021
Completion
Date:
January 2023
Construction
Start Date: April 2023
Projected Completion Date:
September 2024