Tompkins Square Park Field House Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    97% complete

This project will reconstruct the field house in Tompkins Square Park.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2019
Projected Completion Date: March 2020
Completion Date: October 2020

Procurement

Start Date: October 2020
Projected Completion Date: June 2021
Completion Date: January 2023

Construction

Start Date: April 2023
Projected Completion Date: September 2024

Understand how we build parks.

Funding

Total Funding: $5,600,000
Funding Source: Mayoral

Location

Tompkins Square Park, Manhattan
East 9th Street between Avenue A and Avenue B
Community Board: 03

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025