Honey Locust Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Honey Locust Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020
Completion Date: December 2021

Construction

Start Date: January 2022
Projected Completion Date: January 2023
Completion Date: September 2022

Understand how we build parks.

Funding

Total Funding: $1,670,000
Funding Source: Mayoral

Location

Honey Locust Park, Manhattan
East 59th Street between 1st Avenue and 2nd Avenue.
Community Board: 08

 

Project Staff

Project Liaison: Steve Simon