Honey Locust Park Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Honey Locust Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
October 2019
Completion Date:
November 2019
Procurement
Start Date: November 2019
Projected Completion Date:
August 2020
Completion
Date:
December 2021
Construction
Start Date: January 2022
Projected Completion Date:
January 2023
Completion Date: September 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Honey Locust Park, Manhattan
East 59th Street between 1st Avenue and 2nd Avenue.
Community Board: 08
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024