Harlem River Park Synthetic Turf Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This contract will reconstruct the synthetic turf field in Harlem River Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2019
Projected Completion Date:
February 2020
Completion Date:
February 2020
Procurement
Start Date: February 2020
Projected Completion Date:
November 2020
Completion
Date:
April 2022
Construction
Start Date: May 2022
Projected Completion Date:
May 2023
Completion Date: September 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Harlem River Park, Manhattan
East 128th Street, Third Avenue Bridge, Harlem River Drive
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project