Bowne Park Plaza Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the plaza adjacent to bocce area with a new passive sitting area, decorative elements and plantings at Bowne Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: January 2021
Completion Date: January 2022

Construction

Start Date: May 2022
Projected Completion Date: May 2023
Completion Date: January 2023

Understand how we build parks.

Funding

Total Funding: $454,000
Funding Source: City Council

Location

Bowne Park, Queens
29th Avenue, 32nd Avenue, 155th Street, 159th Street
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025