Bowne Park Plaza Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the plaza adjacent to bocce area with a new passive sitting area, decorative elements and plantings at Bowne Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2019
Projected Completion Date:
June 2020
Completion Date:
April 2020
Procurement
Start Date: April 2020
Projected Completion Date:
January 2021
Completion
Date:
January 2022
Construction
Start Date: May 2022
Projected Completion Date:
May 2023
Completion Date: January 2023
Understand how we build parks.
Funding
Funding Source: City Council
Location
Bowne Park, Queens
29th Avenue, 32nd Avenue, 155th Street, 159th Street
Community Board: 07
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025