Flushing Meadows Corona Park Synthetic Turf Fields 8 & 9 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct synthetic turf fields 8 & 9 in Flushing Meadows Corona Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2019
Projected Completion Date: September 2020
Completion Date: November 2020

Procurement

Start Date: November 2020
Projected Completion Date: July 2021
Completion Date: March 2023

Construction

Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: September 2024

Understand how we build parks.

Funding

Total Funding: $8,000,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park, Queens
College Point Boulevard between Fowler Avenue and Booth Memorial Avenue
Community Board: 03, 04, 06, 07, 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024