Al Stabile Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Al Stabile Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2019
Projected Completion Date: March 2020
Completion Date: March 2020

Procurement

Start Date: March 2020
Projected Completion Date: December 2020
Completion Date: March 2022

Construction

Start Date: August 2022
Projected Completion Date: July 2023
Completion Date: July 2023

Understand how we build parks.

Funding

Total Funding: $1,341,000
Funding Source: City Council

Location

Al Stabile Playground, Queens
Centreville Street between 133rd Avenue and 103rd Street
Community Board: 10

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025