Al Stabile Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Al Stabile Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2019
Projected Completion Date:
March 2020
Completion Date:
March 2020
Procurement
Start Date: March 2020
Projected Completion Date:
December 2020
Completion
Date:
March 2022
Construction
Start Date: August 2022
Projected Completion Date:
July 2023
Completion Date: July 2023
Understand how we build parks.
Funding
Funding Source: City Council
Location
Al Stabile Playground, Queens
Centreville Street between 133rd Avenue and 103rd Street
Community Board: 10
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025