Greenbelt Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will partially reconstruct the Greenbelt Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2016
Projected Completion Date: October 2018
Completion Date: March 2020

Procurement

Start Date: March 2020
Projected Completion Date: December 2020
Completion Date: June 2022

Construction

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: May 2024

Understand how we build parks.

Funding

Total Funding: $1,498,000
Funding Source: Mayoral

Location

Blood Root Valley, Staten Island
Brielle Avenue between Wolcott Avenue and Rockland Avenue
Community Board: 02

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024