Noble Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play area at Noble Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2019
Projected Completion Date:
February 2020
Completion Date:
February 2020
Procurement
Start Date: February 2020
Projected Completion Date:
November 2020
Completion
Date:
March 2022
Construction
Start Date: May 2022
Projected Completion Date:
May 2023
Completion Date: May 2023
Understand how we build parks.
Funding
Funding Source: City Council
Location
Noble Playground, Bronx
Noble Avenue, Bronx River Avenue, Bronx River Parkway, Cross Bronx Expressway
Community Board: 09
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024