La Guardia Playground Reconstruction Phase 2

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the children's play area (northern parcel) at La Guardia Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: February 2020
Completion Date: March 2021

Construction

Start Date: June 2021
Projected Completion Date: June 2022
Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $3,253,000
Funding Source: Mayoral

Location

La Guardia Playground, Brooklyn
Roebling Street, South 4th Street, Brooklyn Queens Expressway
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives