La Guardia Playground Reconstruction Phase 2
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the children's play area (northern parcel) at La Guardia Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2018
Projected Completion Date:
April 2019
Completion Date:
May 2019
Procurement
Start Date: May 2019
Projected Completion Date:
February 2020
Completion
Date:
March 2021
Construction
Start Date: June 2021
Projected Completion Date:
June 2022
Completion Date: June 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
La Guardia Playground, Brooklyn
Roebling Street, South 4th Street, Brooklyn Queens Expressway
Community Board: 01
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024