Kissena Park Green Infrastructure Construction
-
100% complete
-
100% complete
-
97% complete
This project will construct green infrastructure to capture storm water at Kissena Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2018
Projected Completion Date:
January 2020
Completion Date:
March 2021
Procurement
Start Date: March 2021
Projected Completion Date:
December 2021
Completion
Date:
April 2023
Construction
Start Date: April 2023
Projected Completion Date:
September 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Kissena Park, Queens
Kissena Boulevard and Booth Memorial Avenue
Community Board: 07
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024