Marcy Green Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Marcy Green Park. Marcy Green North will include a spray shower, lawn, and seating areas. Marcy Green Center will include seating areas and ping pong tables, and Marcy Green South will include a new dog run.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: June 2020

Procurement

Start Date: June 2020
Projected Completion Date: March 2021
Completion Date: March 2022

Construction

Start Date: May 2022
Projected Completion Date: May 2023
Completion Date: April 2023

Understand how we build parks.

Funding

Total Funding: $3,409,000
Funding Source: Mayoral

Locations

  • Marcy Green Center, Brooklyn
    Marcy Avenue, South 4 and South 5 Streets
    Community Board: 01
  • Marcy Green North, Brooklyn
    Marcy Avenue, South 3 and South 4 Streets
    Community Board: 01
  • Marcy Green South, Brooklyn
    Broadway, Marcy Avenue and South 5 Street
    Community Board: 01
 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024