Marcy Green Park Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Marcy Green Park. Marcy Green North will include a spray shower, lawn, and seating areas. Marcy Green Center will include seating areas and ping pong tables, and Marcy Green South will include a new dog run.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2019
Projected Completion Date:
June 2020
Completion Date:
June 2020
Procurement
Start Date: June 2020
Projected Completion Date:
March 2021
Completion
Date:
March 2022
Construction
Start Date: May 2022
Projected Completion Date:
May 2023
Completion Date: April 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Marcy Green Center, Brooklyn
Marcy Avenue, South 4 and South 5 Streets
Community Board: 01 -
Marcy Green North, Brooklyn
Marcy Avenue, South 3 and South 4 Streets
Community Board: 01 -
Marcy Green South, Brooklyn
Broadway, Marcy Avenue and South 5 Street
Community Board: 01
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025