William Sheridan Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct William Sheridan Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: October 2020
Completion Date: December 2021

Construction

Start Date: March 2022
Projected Completion Date: March 2023
Completion Date: June 2023

Understand how we build parks.

Funding

Total Funding: $8,000,000
Funding Source: Mayoral

Location

William Sheridan Playground, Brooklyn
Grand Street, Wythe Avenue, South 1st Street
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024