William Sheridan Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct William Sheridan Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2018
Projected Completion Date:
October 2019
Completion Date:
January 2020
Procurement
Start Date: January 2020
Projected Completion Date:
October 2020
Completion
Date:
December 2021
Construction
Start Date: March 2022
Projected Completion Date:
March 2023
Completion Date: June 2023