Charlie's Place Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball and handball courts, provide fencing, water supply and construct a new entrance along Ellery Street at Charlie's Place.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2019
Projected Completion Date: April 2020
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: October 2020
Completion Date: January 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023
Completion Date: November 2022

Understand how we build parks.

Funding

Total Funding: $1,057,000
Funding Sources:
  • City Council
  • Mayoral

Location

Charlie's Place, Brooklyn
Hopkins Street, Tompkins Avenue, Ellery Street, Throop Avenue
Community Board: 03

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024