P.S. 125 Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct P.S. 125 Playground, including the basketball half-courts, play equipment, safety surfacing, lighting, and benches.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2018
Projected Completion Date:
September 2019
Completion Date:
August 2020
Procurement
Start Date: August 2020
Projected Completion Date:
May 2021
Completion
Date:
July 2022
Construction
Start Date: September 2022
Projected Completion Date:
September 2023
Completion Date: September 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
P.S. 125 Playground, Brooklyn
Rockaway Avenue between Blake Avenue and Dumont Avenue
Community Board: 16
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024