P.S. 125 Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct P.S. 125 Playground, including the basketball half-courts, play equipment, safety surfacing, lighting, and benches.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2018
Projected Completion Date: September 2019
Completion Date: August 2020

Procurement

Start Date: August 2020
Projected Completion Date: May 2021
Completion Date: July 2022

Construction

Start Date: September 2022
Projected Completion Date: September 2023
Completion Date: September 2023

Understand how we build parks.

Funding

Total Funding: $806,000
Funding Source: Mayoral

Location

P.S. 125 Playground, Brooklyn
Rockaway Avenue between Blake Avenue and Dumont Avenue
Community Board: 16

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024