Ocean Hill Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the multipurpose play area and sports courts at Ocean Hill Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2019
Projected Completion Date:
September 2020
Completion Date:
November 2020
Procurement
Start Date: November 2020
Projected Completion Date:
August 2021
Completion
Date:
May 2022
Construction
Start Date: July 2022
Projected Completion Date:
July 2023
Completion Date: December 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Ocean Hill Playground, Brooklyn
Dean Street and Bergen Street between Rockaway Avenue and Thomas S. Boyland Street
Community Board: 16
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024