Ocean Hill Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the multipurpose play area and sports courts at Ocean Hill Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2019
Projected Completion Date: September 2020
Completion Date: November 2020

Procurement

Start Date: November 2020
Projected Completion Date: August 2021
Completion Date: May 2022

Construction

Start Date: July 2022
Projected Completion Date: July 2023
Completion Date: December 2023

Understand how we build parks.

Funding

Total Funding: $5,400,000
Funding Source: Mayoral

Location

Ocean Hill Playground, Brooklyn
Dean Street and Bergen Street between Rockaway Avenue and Thomas S. Boyland Street
Community Board: 16

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024