Lincoln Terrace Park Pavement Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct path pavements and seating areas in Lincoln Terrace Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2018
Projected Completion Date:
September 2019
Completion Date:
October 2019
Procurement
Start Date: October 2019
Projected Completion Date:
July 2020
Completion
Date:
January 2022
Construction
Start Date: February 2022
Projected Completion Date:
February 2023
Completion Date: March 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Lincoln Terrace / Arthur S. Somers Park, Brooklyn
Eastern Parkway, Rochester Avenue, East New York Avenue, Portal Street
Community Board: 08
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025