Lincoln Terrace Park Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct path pavements and seating areas in Lincoln Terrace Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2018
Projected Completion Date: September 2019
Completion Date: October 2019

Procurement

Start Date: October 2019
Projected Completion Date: July 2020
Completion Date: January 2022

Construction

Start Date: February 2022
Projected Completion Date: February 2023
Completion Date: March 2023

Understand how we build parks.

Funding

Total Funding: $3,456,000
Funding Source: Mayoral

Location

Lincoln Terrace / Arthur S. Somers Park, Brooklyn
Eastern Parkway, Rochester Avenue, East New York Avenue, Portal Street
Community Board: 08

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025