Lion's Pride Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Lion's Pride Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2018
Projected Completion Date: August 2019
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020
Completion Date: January 2022

Construction

Start Date: March 2022
Projected Completion Date: March 2023
Completion Date: April 2023

Understand how we build parks.

Funding

Total Funding: $4,115,000
Funding Sources:
  • City Council
  • Mayoral

Location

Lion's Pride Playground, Brooklyn
Van Sinderen Avenue, Riverdale Avenue, Snediker Avenue
Community Board: 05

 