Lion's Pride Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Lion's Pride Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2018
Projected Completion Date:
August 2019
Completion Date:
November 2019
Procurement
Start Date: November 2019
Projected Completion Date:
August 2020
Completion
Date:
January 2022
Construction
Start Date: March 2022
Projected Completion Date:
March 2023
Completion Date: April 2023
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Lion's Pride Playground, Brooklyn
Van Sinderen Avenue, Riverdale Avenue, Snediker Avenue
Community Board: 05
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project